Determining Force Majeure During Ship Construction and Proactively Mitigating Operational Risks of Shipyards
—— Dispute Over Shipbuilding Contract Between China Ping An Property Insurance Co., Ltd. Jiangsu Branch and Yangzhou Longhe Shipbuilding Co., Ltd.
Key Word: Force majeure; Sudden gale; Burden of proof; Wind-prevention measures; Subrogation claim
Case Summary:
In August 2019, Yangzhou Longhe Shipbuilding Co., Ltd. (hereinafter referred to as "Longhe"), as the builder, and Hengfa Company, as the owner, entered into a "Shipbuilding Processing Order