Fairly Determining of Intermediary Fee Payment Conditions to Regulate the Order of the Offshore Vessel Leasing Market
—— Case of Dispute over Intermediary Contract between Jiangsu Yufeng Maritime Engineering Co., Ltd. and Mr. Wei Key Word:Brokerage contract; Intermediary fee conditions; Vessel leasing; Actual performance; Purpose frustrated Case Summary: In 2021, in order to undertake the installation of wind turbines for offshore wind power projects, Mr. Wei negotiated the lease of offshore wind turbine lifting vessels with Jiangsu Yufeng Maritime
Update: 2026-04-22
Determining the Invalidity of Contracts to Regulate the order of Offshore Wind Power Engineering Construction
—— Dispute between Jiangsu Longyuan Zhenhua Marine Engineering Co., Ltd., and Shengzhi Wind Power Technology (Shanghai) Co., Ltd., and Zhongcheng Non-Financial Guarantee (Shenzhen) Co., Ltd. Key Word:Offshore wind power project; Lack of qualifications; Contract invalidity; Refund of advance payment; Guarantee invalidity Case Summary: In June 2021, Jiangsu Longyuan Zhenhua Marine Engineering ., Ltd. (hereinafter referred to as "Longyuan Co., Ltd.") signed an Engineering Construction Contract with Shengzhi Wind Power
Update: 2026-04-16
Accurately Defining the Contract Termination Liabilities to Resolve the Long-Term Dispute between Supply Chain Companies
—— Case of Dispute over Ship Materials and Spare Parts Supply Contract between Taizhou Port and Shipping Transportation Co., Ltd. and Taizhou Zhongran Clean Energy Co., Ltd. Key Word:Supply contract termination; Equipment value refund; Final settlement; Related litigation; Supply-chain stability Case Summary: In October 2015, Taizhou Port and Shipping Transportation Co., Ltd. (hereinafter referred to as "Port and Shipping Transportation Co., Ltd.") entered into a contract with Taizhou Zhongran Clean
Update: 2026-04-06
Confirming Undesignated Contractual Costs, Ensuring the Sound Operation of the Shipbuilding Market
—— Shanghai Changhang Minnan Shipyard vs. Haikun Shipping Co., Ltd., and Others Ship Refurbishment Contract Case Key Word:Ship refurbishment contract; Dock fees; Shore power fees; Unspecified costs Case Summary: In 2015, Haikun Shipping Co., Ltd. (hereinafter referred to as "Haikun Shipping") and others, acting as the contracting party for ship repairs, signed an agreement with Shanghai ChanghangMinnan
Update: 2026-03-20
Determining the subject of Safety Production Liability and Ensuring Orderly Construction of Ships
—— Ping An Property&Casualty Insurance Company of China., Ltd. v. Taixing Transport Machinery Factory Shipbuilding Insurance Contract Subrogation Case Key Word: Safety production liability; Subcontracted work; Hot work; Shipbuilding insurance; Insurer’s recourse Case Summary: Yangzhou COSCO Heavy Industry Co., Ltd. (hereinafter referred to as "COSCO") signed a "Supply Contract" with Taixing Transport Machinery Factory (hereinafter referred to as
Update: 2026-03-11
Legally Recognizing Priority Payment Rights - Resolving Disputes over Shipbuilding Advances
—— Taizhou Hailing District Hengxing Shipyard vs. Mr. Huo, Mr. Guo, and Henan Changtai Container Shipping Co., Ltd. Shipbuilding Contract Dispute Key Word:Advance-funded shipbuilding; Priority of payment; Ship lien; Quality dispute; Mortgage auction Case Summary: In 2014, Mr. Huo entered into a shipbuilding contract with Hengxing Shipyard, stipulating the construction of a bulk cargo ship through the supplied material processing method. After completion
Update: 2026-03-05